Operations & Maintenance

Ongoing work to maintain our flood defense systems

Data source: Mar 2026 SITREP

Permits Issued (Feb)
25permits

Source: Mar 2026 SITREP

Hurricane Gate Inspections
45/ 100% complete

Source: Mar 2026 SITREP

Valve Exercises
92/ 100% complete

Source: Mar 2026 SITREP

PCCP Repairs

Most items near completion pending final acceptance.

All 17 pumps remain available. Repair work does not impact pumping capacity.

Managed by: JV/USACE

Permits Issued

Monthly Permits Trend

MonthPermits IssuedSource
September 202525Oct 2025 SITREP
October 202550Nov 2025 SITREP
November 202546Dec 2025 SITREP
December 202510Jan 2026 SITREP
January 202642Feb 2026 SITREP
February 202625Mar 2026 SITREP

Source: SITREPs

Routine Maintenance Activities

Current Maintenance Work

  • USACE annual inspections completed with no issues identified
  • 17 structural repairs completed across Lakefront Seawall and HSDRRS system
  • Second levee access gate installed at Violet Canal; fabrication underway for Deslonde Street gate
  • Quarterly valve exercises 92% complete

Source: Mar 2026 SITREP